01/06/10
We weren’t able to get pictures of the new house the last few days because the workers were furiously getting a lot of work done on it. Here’s picture proof! Brick, drywall, cabinets, and garage doors are all done! More pictures at the picture page. ![]() ![]() ![]() -Travis 12/31/09
12/06/09
Visible progress continues! ![]() ![]() ![]() 12/01/09
11/18/09
The Fitzgerald house 1.0 is now for sale. The Fitzgerald house 2.0 has its foundation framed, and the builder expects to have the foundation poured and the framing up before the Thanksgiving holiday. Change can be good! |